Risk Analysis of Delayed Departure of Cement Trucks and Proposed Improvements Using Fishbone Diagram and FMEA

Authors

Mohamad Lubabul Khadik , Efta Dhartika Priyana , Purwanto

DOI:

10.46729/ijstm.v7i6.1517

Published:

2026-11-11

Downloads

Abstract

Delays in truck departures can disrupt distribution processes and affect a company’s operational targets. This study aims to identify the causes of cement truck departure delays on the Rembang route at PT Semen Indonesia Logistik and to determine improvement priorities using a Fishbone Diagram and Failure Mode and Effects Analysis (FMEA). A descriptive approach with qualitative and quantitative analysis was applied, using operational departure data for May–July 2026, observations, and assessments by two experts. Of 265 departures, 41 were delayed (15.5%). The Fishbone Diagram grouped the causes into five categories: Man, Method/Environment, Machine, Operational, and Administration. The FMEA showed that receiving warehouse stock constraints (level stock) had the highest Risk Priority Number (RPN) of 392 (S = 8, O = 7, D = 7), followed by prolonged parking time (378) and vehicle breakdowns (RSK) (270). Level stock and prolonged parking were the main improvement priorities, together accounting for 32 of 41 delays (78%), while vehicle breakdowns remain under monitoring because of their highest severity.

Keywords:

Fishbone Diagram, FMEA, Departure Delay, RPN, Cement Truck.

References

[1]. Al-Shboul, M.A. (2017). Infrastructure framework and manufacturing supply chain agility: The role of delivery dependability and time to market. Supply Chain Management, 22(2), 172–185.https://doi.org/10.1108/SCM-09-2016-0335

[2]. Amalia, Purnawan, & Rahman, AZ (2025). Analysis of delays in the distribution of food aid rice by Perum Bulog Kancab Bima using the Six Sigma method. Logistik, 18(1), 165–179.https://doi.org/10.21009/logistik.v18i01.54198

[3]. Budiyani, YA, & Hartini, S. (2025). Analysis of delays in bulk cargo distribution from ship to warehouse using the fishbone diagram and 5W+1H methods (Case study: PT XYZ). Industrial Engineering Online Journal, 14(1).https://ejournal3.undip.ac.id/index.php/ieoj/article/view/49003

[4]. Bushuev, M.A. (2018). Delivery performance improvement in two-stage supply chain. International Journal of Production Economics, 195, 66–73.https://doi.org/10.1016/j.ijpe.2017.10.007

[5]. Fatah, KMA, Rifqiani, PS, Lukman, I., Sidiq, A., & Wardana, MW (2025). Analysis of causes of late delivery of cardboard sheet products using FMEA method and solution recommendations in the cardboard sheet industry. Journal of Engineering, Technology, and Science, 9(2), 803–810.https://doi.org/10.33024/jrets.v9i2.21518

[6]. Hapiuzin, N., Supriyadi, E., & Wahyu. (2022). Evaluation of factors causing delays in delivery of goods to meet customer demand using the Failure Mode and Effect Analysis (FMEA) method. TECHNOLOGY: Scientific and Technological Journal, 5(2), 153–160.https://openjournal.unpam.ac.id/index.php/TKG/article/view/48136

[7]. Hersanto, CM, Adiningrum, NTR, & Sumarna, DL (2023). Analysis of the causes of late delivery of goods at Pos Express using the Six Sigma method. Logistics, 16(1), 42–53.https://journal.unj.ac.id/unj/index.php/logistik/article/download/34614/15161

[8]. Khairansyah, MD, Amrullah, HN, & Qurratuláini, NF (2024). Overhead crane failure risk assessment using Failure Mode and Effect Analysis (FMEA) and fishbone diagram methods. Journal of Occupational Health and Environmental Safety, 5(2), 93–101.https://doi.org/10.25077/jk3l.5.2.93-101.2024

[9]. Muttaqin, AZ, & Kusuma, YA (2018). Failure Mode and Effect Analysis of Project X in Madiun City. JATI UNIK, 1(2), 81–96.https://ojs.unik-kediri.ac.id/index.php/jatiunik/article/download/118/89/269

[10]. Nelfiyanti, Setiawan, B., & Setiawan, A. (2024). Analysis of factors causing delays in product delivery to consumers using the FMEA method at PT. MRP. National Seminar on Science and Technology 2024, 1–9.https://jurnal.umj.ac.id/index.php/semnastek/article/download/22660/10477

[11]. Niemi, T., Hameri, A.-P., Kolesnyk, P., & Appelqvist, P. (2020). What is the value of delivering on time? Journal of Advances in Management Research, 17(4), 473–503.https://doi.org/10.1108/JAMR-12-2019-0218

[12]. Pangestuti, DC, Nastiti, H., & Husniaty, R. (2022). Operational risk analysis using the FMEA method. Journal of Accounting, Economics and Business Management, 10(2), 177–186.https://doi.org/10.30871/jaemb.v10i2.3235

[13]. Rollandiaz, S., & Iskandar, YA (2024). Evaluation of fuel product delivery delays using Lean Six Sigma. INFOTECH Journal, 10(1), 74–83.https://doi.org/10.31949/infotech.v10i1.8796

[14]. Somadi, S. (2020). Evaluation of late delivery of goods using the Six Sigma method. Indonesian Logistics Journal, 4(2), 81–93.https://doi.org/10.31334/logistik.v4i2.1110

A. Wicaksono, ED Priyana, and YP Nugroho, “Quality control analysis using the Failure Mode and Effects Analysis (FMEA) method on centrifugal pumps at PT. X,” Jurnal Teknik Industri, vol. 9, no. 1, pp. 177–185, 2023.

Author Biographies

Mohamad Lubabul Khadik, Prodi Teknik Industri, Fakultas Teknik, Universitas Muhammadiyah Gresik, Indonesia

Author Origin : Indonesia

Efta Dhartika Priyana, Prodi Teknik Industri, Fakultas Teknik, Universitas Muhammadiyah Gresik, Indonesia

Author Origin : Indonesia

Purwanto, Prodi Teknik Industri, Fakultas Teknik, Universitas Muhammadiyah Gresik, Indonesia

Author Origin : Indonesia

Downloads

Download data is not yet available.

How to Cite

Lubabul Khadik, M., Efta Dhartika Priyana, & Purwanto. (2026). Risk Analysis of Delayed Departure of Cement Trucks and Proposed Improvements Using Fishbone Diagram and FMEA. International Journal of Science, Technology & Management, 7(6), 725–734. https://doi.org/10.46729/ijstm.v7i6.1517

Most read articles by the same author(s)