Analysis of the Causes of Delays in Cement Delivery at CP Tuban Using the FTA and FMEA Methods at PT XYZ
DOI:
10.46729/ijstm.v7i6.1526Published:
2026-11-18Downloads
Abstract
On-time delivery is a key indicator for maintaining smooth supply chain operations and ensuring customer satisfaction in cement distribution. However, between May and August 2026, cement shipments from CP Tuban experienced 3,420 instances of delay, primarily due to issues related to inventory levels, the goods release process, and excessive parking duration. This study aims to identify the causes of these delivery delays, determine which causes require the most urgent attention, and propose improvements. The Fault Tree Analysis (FTA) method is used to map the causes of delays into a hierarchical structure, while Failure Mode and Effects Analysis (FMEA) is employed to assess the risk of each cause via a Risk Priority Number (RPN). Data were collected through interviews with the General Manager and the Head of the Logistic Control Tower team, questionnaires assessing severity, occurrence, and detection (completed by two respondents), as well as On-Time Delivery (OTD) data and Root Cause Analysis (RCA). The FTA identified 14 basic events categorized under warehouse constraints, driver-related issues, and accidents all linked via OR gates, meaning each can directly lead to a delay. The FMEA yielded RPN values ranging from 48 to 448, with the four highest-priority issues being: failure to adhere to maintenance schedules (448), failure to complete equipment checklists (392), drivers neglecting to provide confirmation via the application (378), and drivers taking excessively long breaks (324). Improvements are proposed using the 5W+1H framework, including automated maintenance schedule reminders, mandatory digital equipment checklists to be completed prior to departure, automated confirmation prompts within the driver application, and automated notifications combined with the tracking of driver parking duration. The combination of FTA and FMEA not only identifies the causes of delays but also determines which causes should be prioritized for improvement.
Keywords:
delivery delay, Fault Tree Analysis, Failure Mode and Effects Analysis, Risk Priority Number and cement logistics.References
[1] R. Luthfi Firdaus and G. Hapsak Pradipto, "Analysis of the Causes of Delivery Delays at Indah Logistik Cargo Agents (ILC) Pillars Using the DMAIC Method,” Journal of Applied Industrial Technology and Management (JTMIT), Vol. 5, No. 2, Pp. 1111–1121, 2026.
[2] D. Hariani and M. Ramdany, “The Influence of Planning, Quality Control, and Evaluation of Logistics Management Performance on the Timeliness of Goods Delivery at PT.ID.Express Logistik Indonesia, Depok Warehouse,” Vol. 7, No. 7, P. 11, 2022, [Online]. Available: www.Topbrand-Award.Com
[3] R. Rossidha, K. Soliha, and E. Sulistyowati, “Analysis of the Causes of Delays in Delivery of Finished Products PT. Xyz Using Failure Mode and Effect Analysis (FMEA) Method,” Jurnal Sains Dan Teknologi: Jurnal Keilmuan Dan Aplikasi Teknologi Industri, Vol. 25, No. 2, Pp. 435–444, Dec. 2025, Doi: 10.36275/Ec7qhy37.
[4] KMA Fatah, I. Lukman, A. Sidiq, and MW Wardhana, "Analysis of the Causes of Delays in Delivery of Cardboard Sheet Products Using theFMEA and Solution Recommendations in the Cardboard Sheet Industry,” Journal of Engineering, Technology, and Science, Vol. 9, No. 2, Pp. 803–810, Aug. 2025, Doi: 10.33024/Jrets.V9i2.21518.
[5] G. Misrina Mardhotilah, M. Rizal,And R. Tahir, “Handling of Inter-Delivery Failures Using Failure Mode and Effect Analysis (FMEA) and Fault Tree Analysis (FTA) Methods: A Study of a Shipping Company,” 2024. [Online]. Available: Http://Jiip.Stkipyapisdompu.Ac.Id
[6] D. Lorenza and T. Rahman, "Analysis of the Causes of Delays in the Cradle Project Production Process Using the Fault Tree Analysis Method"(FTA)," Logistica Journal, Vol. 1, No. 2, 2023.
[7] M. Yolanda, Y. Ekawati, and S. Noya, “Application of Fault Tree Analysis Method to Prevent Failure in Interior Department at PTX,” Journal of Science and Application of Industrial Engineering (Sakti), Vol. 3, No. 1, Pp. 49–58, Jun. 2023, Doi: 10.33479/Jtiumc.V3i1.49.
[8] R. Amalia, M. Rohman, and C. Nurcahyo, "Analysis of the Causes of Delays in the Sidoarjo Town Square Development Project Using the Fault Tree Analysis Method (FTA),” Jurnal Teknik ITS, Vol. 1, No. 1, Pp. 20–23, 2021.
[9] A. Andriyanto, Y. Ega, and A. Putri, "Analysis of the Causes of Failure to Deliver Goods in Project 247"Or Type of Sxq in the Airfreight Operation Division of PT. Cipta Krida Bahari Using Failure Mode and Effect Analysis (FMEA) and Fault Tree Analysis (FTA) Methods,” Jurnal Logistik Bisnis, Vol. 11, No. 01, 2021, [Online]. Available: Https://Ejurnal.Poltekpos.Ac.Id/Index.Php/Logistik/Index
[10] HN Wahyudi, RB Ulum, and PA Wibowo, "Analysis of Quality Control of Wooden Window Products Using the Fault Tree Analysis Method (FTA) and Failure Mode and Effect Analysis (FMEA) at CV Arafah Jaya Purwakarta,” Jurnal Teknik Industri Terpadu, Vol. 8, No. 3, Pp. 3413–3423, Jul. 2025, Doi: 10.31004/Jutin.V8i3.48300.
[11] S. BastutiAnd Surya Kencana, “Implementation of FTA and Factor Analysis to Reduce Logistics Supply Delays in Construction Companies,” Vol. Xviii, No. 2, Pp. 241–252, 2024.
[12] Nelfiyanti, B. Setiawan,And A. Setiawan, “Analysis of Product Delivery Delay Factors to Consumers Using the FMEA Method at PT.Mrp,” Proceedings of the 2024 National Technology Seminar, 2024.
[13] D. Wijaya, Y. Praharsi, and D. Maulana, “Controlling Delays in Delivery of Goods Using the MethodFTA and FMEA," Maritime Business Management Conference, Vol. 1, No. 1, 2022.
[14] A. Dika Fista LamandaAnd I. Kirono, “Analysis of Factors Causing Package Delivery Failure Using the FTA and FMEA Methods at PT Xyz,” 2026.
[15] A. Azzam, SM Ridwan, Y. Sukmono, and FD Sitania, "Risk Analysis and Determination of Mitigation Strategy for the Goods Delivery Process Using theFMEA (Case Study of PT.
[16] A. Wicaksono, ED Priyana, and YP Nugroho, “Quality control analysis using the Failure Mode and Effects Analysis (FMEA) method on centrifugal pumps at PT. X,” Jurnal Teknik Industri, vol. 9, no. 1, pp. 177–185, 2023.
[17] Purwanto, P., Ningrum, DW, Hakim, MN, & Qulub, MT (2026). Proposed Integrated Assessment of RULA, REBA, and OWAS for Ergonomic Risk Evaluation and Workstation Improvement. Andalasian International Journal of Applied Science, Engineering and Technology, 6(2), 182–191.https://doi.org/10.25077/aijaset.v6i2.337
[18] Purwanto, P., Amrullah, E., Hidayat, H., Jufriyanto, M., Rizqi, AW, & Khoirunnisaa, AZ (2026). The Influence of Culture on Operator Flexibility through Work Autonomy: Ergonomics and Leadership Perspectives. Matrik: Journal of Management and Industrial Production Engineering, 27(1), 21–30.https://doi.org/10.30587/matrik.v27i1.12213
[19] R. Bachtiar, YP Negoro, and Purwanto, “Risk Analysis of Water Distribution Pipe Leakage at Perumda Giri Tirta Gresik Using FMEA and FTA Methods,” INTECOMS: Journal of Information Technology and Computer Science, Vol. 9, No. 3, Pp. 686–694, 2026,https://doi.org/10.31539/kgd0t167.
License
Copyright (c) 2026 International Journal of Science, Technology & Management

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.